Part Number:TLV320AIC34
Hi Team,
My customer is looking at TLV320AIC34 and have a question on the power sequencing.
We see that the datasheet recommends the following power up sequence: IOVDD->AVDD/DRVDD->DVDD.
The customer would like to power up with this sequence: AVDD,DRVDD(Power at the same time) -> IOVDD, DVDD(power at the same time).
The datasheet says the device is extremely tolerant to power supply sequencing, so we're trying to better understand if the above sequence is valid and how much risk is involved with this sequence?
Thanks for your help!